Page 10 - KNT
P. 10

05











           Sensitive Transport






















            There are times when we handle   when the deck of feeder vessel is leveled   the stoppers of chassis and modules
           projects that include coastal barge   even with pier ground.        carrying subject shipment MUST be
           shipping of heavy-weight and lengthy                                tightly locking their wheels. ---even
           cargoes. Though such transport     Furthermore, when the currently-  more amount of time and equipment
           method consumes less time, it is more   frequented Roll on and Roll off method   should be invested to secure the
           exposed to greater risk and possesses   (or known as Ro/Ro method) is being   shipment
           timely limitations such as having to   used, one must finalize the performance
           precisely arrive in time for berthing of   level of ballast pump of subject barge    This project was in last September
           mother vessel. Therefore, concerned   ship, engineered loading procedure and   ---ocean transport to waters of the
           personnel are required to continuously   positions of every cargo to execute the   Persian Gulf after coastal barge shipping
           monitor the movement of subject   whole procedure in one flow. It should be   from Gunsan port to Masan port.
           shipment to administer systematically   performed very smoothly and flawlessly
           in terms of time.                 because the Ro/Ro method allows more     Delivery Duration : 1.5 days
                                             danger to cargoes --–though barge             Max. 141mt
            Coastal barge transports, particularly   shipping is still very time-efficient,   Max. Length 30meter
           ones departing from east coast of Korea,   cost-effective and safe as long as is
           demand great consideration on its   properly performed--- considerable
           geographical characteristic ---large tidal   amount of time, expertise, and equip-
           range---- when selecting the most   ment should be invested in lashing and
           suitable time for loading/discharging;   securing of the cargoes to the deck. Like
   5   6   7   8   9   10   11   12   13   14   15