05 Safe Delivery of 5600Ton Press Line to Romania
the opportunity to prove us to 14th August 2019. Discharging
❶ Hyundai Rotem pitesti be a right solution provider as a took just 3 days and custom
5600Ton XL Press Line logistics specialist. clearance for 2 weeks. In-land
❷ Q’TY: 214Pkgs, 2,151,080Kgs,
trucking was commenced from
5,711Cbm
In completing a project for 31st August. Finally, all transport
❸ Dangjin, Korea / Constanza,
Renault Dasia T/D press line, KNT for the Dasia project until the
Romania
Cargo proved itself to be the right final destination was completed
❹ Final destination: Renault
Dasia, Romania specialized transport partner. on 27th September 2019. trucking plan. We planned
❺ Work scope: Ocean & Inland Months of planning resulted in trucking order to minimize
transport at Romania a smooth, successful job and As any special projects, there the number of truck for
another satisfied customer. Our was difficulty to perform this reducing price. We had lots
ince the beginning of 2019, task was not only to transport the shipment. It is never always fair of experience about those
S we had prudent discussion T/D press to Constanza, Romania and easy. After we completed problems so that our Korea
with our client regarding but also to transport them to transport contract with client, head office always send staff
press line shipment transport. the final destination by truck. they informed that cargo should to the site. Mr. Kim, Managing
Finally, Knt cargo was awarded we could perform this business be arrive at final job site in the director, was dispatched to
a contract with cargozone, successfully. order assembly sequence due Romania. He controlled truck
who was a longtime partner to small space yard. In other transport order as well as
and had maintained a strong Cargo was loaded onto MV New word, client wanted to assemble cooperated with client request.
business partner, to transport legend Saphire on 06th June machine smoothly by control The inland transport carried out
5,600 Ton High speed press line 2019. Transit time from Korea to cargo arrival time. It means for 1month. There was no any
manufactured by Hyundai Rotem Romania was 47 days. The vessel that the number of trucks could problem under Mr. Kim’s control.
to Renault Dasia, Romania. It was arrive at Constanza, Romania on be increased more than our
Automobile Dacia S.A. is a The Port of Constanța is located
Romanian car manufacturer that in Constanța, Romania, on the
takes its name from the historic western coast of the Black Sea.
region that constitutes the
present-day Romania.